Physical Progress
90%
Approved Budget
KES 8,500,000
Allocated (Current FY)
KES 8,500,000
Disbursed to PMC
KES 7,225,000
Verified Spent
KES 6,800,000
Absorption Rate
94.1%

8-Point Project Transparency Profile

Kenya Constitution Art. 35 Verified

Public transparency index answering the 8 core citizen accountability dimensions mandated by Section 23 of the NG-CDF platform guidelines.

1. What is being built?
Establishment of Narok West Constituency Digital Innovation & ICT Hub at Siana (Education & Academic Infrastructure)
2. Where is it located?
Siana Ward • Narok West Constituency NG-CDF
3. Who benefits?
Narok West Digital Innovation Hub (~4,500 citizens)
4. How much does it cost?
Budget: KES 8,500,000
5. How much has been disbursed?
Disbursed: KES 7,225,000 • Spent: KES 6,800,000 (Absorption: 94.1%)
6. What is current status?
Site Handed Over & Civil Works Active • Verified progress: 90%
7. What bottlenecks exist?
No active execution bottlenecks
8. What documents are available?
Engineering drawings & BOQ summary registered

Project Description & Scope of Works

Standard statutory NG-CDF project implemented in Siana Ward, Narok West Constituency, to enhance grassroots public service delivery.

Construction Milestones & Civil Works Schedule

Substructure & Foundation Concrete Works
Weight Contribution: 20%
Verified Complete
Mar 15, 2025
Superstructure Walling & Lintel Ring Beams
Weight Contribution: 25%
Verified Complete
Mar 15, 2025
Roofing Steel Trusses & Prepainted Iron Sheets
Weight Contribution: 25%
Verified Complete
Mar 15, 2025
4
Finishes, Plastering, Glazing, Electrical & Painting
Weight Contribution: 30%
Target: In Progress

Visual Site Documentation Timeline

Site photographs being compiled by the M&E field team.

Project Statutory Documents & BOQs

No official engineering drawings or BOQ files uploaded for this project yet.

Field Monitoring & Inspection Reports

Routine inspection report scheduled for next quarterly audit.

Execution Challenges & Mitigation Actions

No active contractual or physical execution bottlenecks logged for this project.